Historical records during close-out are useful to (    ) and (    ) for future projects.
查看答案
A. Predict trends, highlight problems.
2单选题2 / 40
A clear definition of the user's needs serves as the direct basis for the:
查看答案
B. Functional requirements.
3单选题3 / 40
Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?
查看答案
C. Weak matrix.
4单选题4 / 40
The project charter:
查看答案
E. All of the above.
5单选题5 / 40
The WBS is:
查看答案
B. A task oriented family tree of the project.
6单选题6 / 40
Including the customer in the process of project planning is:
查看答案
B. Essential in the definition and documentation of project goals.
7单选题7 / 40
The scope management provides:
查看答案
D. All of the above.
8单选题8 / 40
During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:
查看答案
D. Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
9单选题9 / 40
Proper implementation of project management will guarantee that:
查看答案
E. None of the above.
10单选题10 / 40
The most difficult decision for the executive sponsors to make at the end-of-phase review meeting is:
查看答案
D. Canceling the project.
11单选题11 / 40
The financial closeout of a project dictates that:
查看答案
D. No further charges can be made against the project.
12单选题12 / 40
A project can best be defined as:
查看答案
D. Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.
13单选题13 / 40
The project scope/charter baseline includes:
查看答案
E. All of the above.
14单选题14 / 40
Scope reporting is the timely determination, (    ), and (    ) of project progress, status data, and transforming this into structured documentation (reports) necessary to judge project performance (reporting on work packages).
查看答案
A. Recording, accumulation.
15单选题15 / 40
The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
查看答案
D. Quality of work.
16单选题16 / 40
The scope baseline once established and approved, is used:
查看答案
D. All of the above.
17单选题17 / 40
The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the (    ) phase of the project but first documented in the project (    ).
查看答案
A. Conceptual, charter/baseline.
18单选题18 / 40
Project management/project planning is most closely aligned with:
查看答案
E. B and C.
19单选题19 / 40
Management decision-making includes:
查看答案
E. All of the above.
20单选题20 / 40
The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
查看答案
C. Tasks.
21单选题21 / 40
A task-oriented family tree of activities is a:
查看答案
C. Work breakdown structure.
22单选题22 / 40
Management plans include all of the following except:
查看答案
E. Scope baseline.
23单选题23 / 40
A comprehensive definition of scope management would be:
查看答案
A. Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
24单选题24 / 40
The process of choosing/documenting the best approach to achieve the project objectives is part of:
查看答案
D. Scope planning.
25单选题25 / 40
A completion of a local government study resides on your critical path. This would most likely be referred to as:
查看答案
C. An external dependency
26单选题26 / 40
Which of the following can affect network durations?
查看答案
E. A and B only
27单选题27 / 40
Sources for data on activity durations and resource requirements can be gathered from which of the following:
查看答案
D. All of the above
28单选题28 / 40
The erection of foundation formwork before the placement of foundation concrete would be an example of a (    ) dependency.
查看答案
B. Mandatory
29单选题29 / 40
"Hard logic" in the preparation of a network refers to:
查看答案
C. Mandatory dependencies
30单选题30 / 40
The difference between a project and a program is that:
查看答案
D. A and C.
31单选题31 / 40
As a control tool, the bar chart (Gantt) methods is most beneficial for:
查看答案
B. depicting actual versus planned tasks
32单选题32 / 40
You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:
查看答案
C. See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis
33单选题33 / 40
Line of balance charts are used most frequently in:
查看答案
C. Manufacturing
34单选题34 / 40
Which of the following is indicative of negative float?
查看答案
A. The late start date is earlier than the early start date.
35单选题35 / 40
The most frequently used construct in Precedent Diagramming Method is:
查看答案
D. Finish to Start.
36单选题36 / 40
The critical path is calculated by
查看答案
B. determining which tasks have the least amount of total slack.
37单选题37 / 40
Using the table in the Special window, Which task is completed?
查看答案
B. remove debris
38单选题38 / 40
Which may be employed to shorten a schedule without changing the scope of the task?
查看答案
A. Fast tracking.
39单选题39 / 40
Resource leveling (    ).
查看答案
E. B or D.
40单选题40 / 40
A(n) (    ) is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.
查看答案
B. Event.