1单选题1 / 40
Which of the following impacts the critical path?
查看答案
A. Changing the task duration.
2单选题2 / 40
The range of time allowed for an activity to be completed in is the (    ).
查看答案
D. Scheduled time (LF - ES).
3单选题3 / 40
Free float is the amount of time that an activity may be delayed with out affecting the (    ).
查看答案
A. Early start of the succeeding activities.
4单选题4 / 40
Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
查看答案
C. 1.8
5单选题5 / 40
In crashing a task, you would focus on:
查看答案
C. Accelerating performance of tasks on critical path.
6单选题6 / 40
Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
查看答案
B. 8.8
7单选题7 / 40
Using the WBS in the Special window, an instance of a work package is:
查看答案
E. None of the above
8单选题8 / 40
All of the following are categories of a milestone in a schedule except:
查看答案
E. Task duration.
9单选题9 / 40
The actual configuration of a PERT/CPM network (    ) the amount of resources that can be devoted to the project.
查看答案
D. Is heavily dependent upon
10单选题10 / 40
Excessive flexibility in specifying requirements will (    ) the likelihood of time overruns.
查看答案
D. Increase
11单选题11 / 40
The key purpose of project control is to:
查看答案
C. Keep the project on track.
12单选题12 / 40
Fast tracking means to:
查看答案
A. Speed up a project through parallel tasks.
13单选题13 / 40
As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
查看答案
C. Unchanged.
14单选题14 / 40
The purpose of a dummy activity in an activity-on-arrow diagram is to:
查看答案
E. Show a dependency relationship.
15单选题15 / 40
On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:
查看答案
C. ¥-150
16单选题16 / 40
A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:
查看答案
B. 33.00%
17单选题17 / 40
Resource leveling will often affect the project by making it:
查看答案
B. Longer
19单选题19 / 40
Using the figure in the Special window, Activity "D" has a latest start time of (    ) weeks and a latest finish time of (    ) weeks.
查看答案
A. 2, 10
20单选题20 / 40
Using the figure in the Special window, Activity "L" has an early start time of (    ) weeks and an early finish time of (    ) weeks.
查看答案
E. 15, 17
22单选题22 / 40
Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
查看答案
A. P
23单选题23 / 40
Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
查看答案
D. 3
25单选题25 / 40
The first step in building a PERT/CPM network is to:
查看答案
D. Create a work breakdown structure
26单选题26 / 40
The critical path in a schedule network is the path that:
查看答案
A. Takes the longest time to complete
27单选题27 / 40
Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:
查看答案
C. A new critical path may appear after the crash.
28单选题28 / 40
Your team has prepared a CPM schedule for your review. You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity). Select the correct statement from the following:
查看答案
A. This is a valid representation if the logic is correct.
29单选题29 / 40
During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
查看答案
C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
30单选题30 / 40
Network schedules are prepared during the (    ) phase and updated during the (    ) phase.
查看答案
B. Development, implementation.
31单选题31 / 40
Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:
查看答案
E. A and B.only.
32单选题32 / 40
Increasing resources on the critical path activities may not always shorten the length of the project because:
查看答案
E. All of the above.
33单选题33 / 40
A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
查看答案
B. 5 weeks
34单选题34 / 40
Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:
查看答案
C. Those activities on the critical path begining with the longest time duration activities.
35单选题35 / 40
A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in:
查看答案
E. A through D are possible based upon where the resources are deployed.
36单选题36 / 40
Bar charts are most appropriate for:
查看答案
A. Comparing actual to planned performance to each activity.
37单选题37 / 40
A non-critical path activity is completed in half the time. Then,
查看答案
B. The slack in the path containing this activity will increase.
38单选题38 / 40
Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the (    ) and identification of the (    ) .
查看答案
A. Slack for each activity, critical path.
39单选题39 / 40
ADM is an activity-on-arrow method. In this method, a dummy activity:
查看答案
B. Denotes any dependency relationship.
40单选题40 / 40
The starting point in the development of a top-down PERT/CPM chart is the (    ) .
查看答案
D. Work breakdown structure.