职业资格类项目管理师PMP美国项目管理PMP

PMP认证考试练习题(23,24)

40 题含答案PMP
共 40 题返回本类
1单选题1 / 40
Work packages are used to:
查看答案
D. All of the above.
2单选题2 / 40
Project life cycles are very useful for (    ) and (    ) .
查看答案
C. Standardization, control
3单选题3 / 40
Which of the following are included as part of a scope statement?
查看答案
D. All of the above
4单选题4 / 40
The initial document that formally recognizes the existence of a project is the (    ) .
查看答案
C. Project charter
5单选题5 / 40
Which of the following is not a scope management process?
查看答案
D. Scope change control
6单选题6 / 40
In which of the following scope management processes is the scope management plan prepared?
查看答案
B. Scope planning
7单选题7 / 40
The project charter is prepared in which scope management process?
查看答案
A. Initiation
8单选题8 / 40
The work breakdown structure (WBS) is first developed in which scope management process?
查看答案
D. Scope Definition
9单选题9 / 40
In which of the following scope management processes are subject matter experts used?
查看答案
A. Initiation
10单选题10 / 40
A Work Berakdown Structure is most useful for:
查看答案
E. A and C.
11单选题11 / 40
The scope statement provides
查看答案
D. All of the above
12单选题12 / 40
A work breakdown structure:
查看答案
D. both A and B.
13单选题13 / 40
Budgetary estimates are the output of the (    ) phase(s) of the project.
查看答案
B. development
14单选题14 / 40
Which of the following are included in the Acquisition phase(s) of the project life cycle.
查看答案
C. execution and phase-out
15单选题15 / 40
Project alternatives are examined during the (    ) phase of the project
查看答案
E. A and C.
16单选题16 / 40
We assign human and non-human resources in the (    ) phase of the budget.
查看答案
D. implementation
17单选题17 / 40
Project trade-offs vary between
查看答案
D. cost, quality and schedule
18单选题18 / 40
The extent of project management techniques to be used on a project are determined mainly by the (    ) and (    ) of the project.
查看答案
D. nature, size
19单选题19 / 40
The time necessary to complete a project is called the (    ) of a project.
查看答案
B. Life Cycle
20单选题20 / 40
When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
查看答案
E. work package
22单选题22 / 40
Which of the following are types of status reports?
查看答案
C. cost, schedule, technical performance
23单选题23 / 40
You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most often overlooked?
查看答案
A. Data item deliverables
24单选题24 / 40
During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform a given task. The best way for the project manager to handle this would be to:
查看答案
B. Let the affected line groups decide among themselves who will perform the work
25单选题25 / 40
The most common definition of project success is:
查看答案
D. Within time, cost, performance and accepted by the customer/user
26单选题26 / 40
The scope of a project can be expected to change if:
查看答案
E. All of the above are possible based upon the situation
27单选题27 / 40
The most common non-behavioral reason for projects being completed behind schedule and over budget is:
查看答案
D. Ill-defined requirements
28单选题28 / 40
The appointment or selection of a project sponsor is often based upon:
查看答案
E. All of the above
29单选题29 / 40
The "rolling wave" or "moving window" concept is used most frequently on projects where:
查看答案
C. The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
30单选题30 / 40
Interfacing with the customer after project go-ahead is the responsibility of:
查看答案
C. Project manager
31单选题31 / 40
Using the WBS shown in the Special window, a typical work package would be:
查看答案
E. None of the above.
32单选题32 / 40
Feasibility studies evaluate alternatives in terms of
查看答案
E. All or part of A through D
33单选题33 / 40
Project tradeoffs are usually made by comparing (    ) and constraints.
查看答案
D. Cost, quality, and technical performance
34单选题34 / 40
The degree to which a company accepts and utilizes project management is often dependent upon the (    ) and (    ) of the project.
查看答案
C. Size, nature
35单选题35 / 40
Project management provides organizations with a methodology to:
查看答案
A. Become more efficient and effective in accomplishing goals that cannot be handled well by the traditional structure
36单选题36 / 40
Configuration (baseline) control monitors performance against the
查看答案
A. scope baseline
37单选题37 / 40
A summary WBS is usually developed in the
查看答案
A. Conceptual phase
38单选题38 / 40
A project may be defined as (    )
查看答案
D. an undertaking with a defined starting point and defined objectives
39单选题39 / 40
Approval to proceed is normally made at the end of the (    ) phase of a typical project.
查看答案
A. conceptual
40单选题40 / 40
Lessons learned are most often based upon project historical records. Lessons learned can be used to:
查看答案
D. All of the above
← 上一卷下一卷 →