you must produce 27 widgets. you can only produce 9 widgets per production run. each production line setup costs $1000. each widget consumes $10 worth of material and $5 worth of labor. what is total variable cost for producing one widget.
查看答案
E. none of the above
2单选题2 / 40
creation of project objectives:
查看答案
E. a and b only
3单选题3 / 40
during which phase of the project life cycle is the amount at stake lowest?
查看答案
A. concept
4单选题4 / 40
techniques that can improve communication include:
查看答案
C. using redundancy (i.e. saying it two different ways) whenever possible
5单选题5 / 40
the delphi method is well-suited for:
查看答案
E. a and b only
6单选题6 / 40
the zero defects concept
查看答案
D. a and c.
7单选题7 / 40
what tool have project managers come to use to identify all of the costs associated with a project.
查看答案
D. a work breakdown structure.
8单选题8 / 40
(    ) is a receipt issued by a carrier for merchandise to be delivered to a party at some destination.
查看答案
D. bill of lading
9单选题9 / 40
a program is characterized as:
查看答案
C. a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.
10单选题10 / 40
contingency planning should include all but which of the following?
查看答案
A. the development of a contingency allowance determined by combining (layering) various estimate segments to form larger estimate segments.
11单选题11 / 40
from an operating or functional perspective, there are various objectives of purchasing and materials management. which is not one of these
objectives?
查看答案
E. to attain approval from each department of every purchase
12单选题12 / 40
in order to achieve long-term quality improvements, management must do the following:
查看答案
C. implement of a formal quality control program with worker and management involvement.
13单选题13 / 40
team members want to work for a project manager that can provide them with career path planning. in which organizational form is career
path planning difficult for project employees?
查看答案
B. pure project
14单选题14 / 40
the swiftest and most effective communications take place among people with
查看答案
A. common points of view
15单选题15 / 40
typically, during which phase in a project life cycle are most of the project expenses incurred.
查看答案
C. execution phase.
17单选题17 / 40
fixed-price contracts place more risk on the (    ) .
查看答案
D. b and c
18单选题18 / 40
the best way to insure quality conformance is to (    ).
查看答案
C. train each worker to implement the work.
19单选题19 / 40
the project charter is developed by:
查看答案
D. both a and c
20单选题20 / 40
when a project manager is running over the budgeted costs, the project manager can typically (    ) to attempt to get the project back on
budget.
查看答案
D. all of the above.
21单选题21 / 40
which of the following fall(s) under the responsibilities of a project manager?
查看答案
E. all of the above
22单选题22 / 40
a legally binding document offered unilaterally is a (    ) .
查看答案
A. purchase order
23单选题23 / 40
a technical requirement has which of the following characteristics:
查看答案
E. typically describe physical dimensions and performance requirements
24单选题24 / 40
if a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project
manager should assume:
查看答案
E. none of the above.
25单选题25 / 40
inspection of a complex project according to specifications is accomplished by (    ).
查看答案
C. quality conformance inspection
26单选题26 / 40
the behavioral responsibilities of a project manager may also include dealing with:
查看答案
E. all of the above
27单选题27 / 40
the difference between the bcws and the bcwp is referred to as the:
查看答案
A. schedule variance
28单选题28 / 40
"paraphrasing" is most closely associated with which part of the communication process?
查看答案
D. feedback
29单选题29 / 40
a gantt chart is useful in determining:
查看答案
B. when a task starts and stops
30单选题30 / 40
a contract originated bilaterally may be developed by (    ) .
查看答案
E. all of the above.
31单选题31 / 40
in a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance
review?
查看答案
D. all of the above
32单选题32 / 40
upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are
referred to as the:
查看答案
A. baseline costs
33单选题33 / 40
which of the following is not a definition to determine a product's ability to operate as intended?
查看答案
E. all are definitions
34单选题34 / 40
a work breakdown structure is most useful for:
查看答案
E. a and c
35单选题35 / 40
reaching an understanding of concessions is accomplished in the (    ) stage of negotiations.
查看答案
D. closure
36单选题36 / 40
the primary consideration of product management is to know the (    ).
查看答案
D. functionality the product will provide over its useful life
37单选题37 / 40
the reason that cost management is so difficult in project management is that:
查看答案
A. projects by definition and nature are non-recurring events and are therefore difficult to predict.
38单选题38 / 40
using visual aids during management/customer presentations will:
查看答案
D. all of the above.
39单选题39 / 40
which of the following organizational forms would be likely to have an individual with the title of vice president for project management?
查看答案
C. matrix
40单选题40 / 40
a contract is legally binding and must comprise all but one of the following:
查看答案
C. approved negotiations