职业资格类项目管理师PMP美国项目管理PMP

PMP认证考试练习题(11,12)

39 题含答案PMP
共 39 题返回本类
1单选题1 / 39
(    ) is associated with a buyer's request for materials or equipment to meet a particular need or accomplish a specific purpose.
查看答案
C. implied warranty of fitness for a particular purpose
2单选题2 / 39
adm is an activity-on-arrow method. in this method, a dummy activity:
查看答案
B. denotes any dependency relationship.
3单选题3 / 39
an informal communication network on a project and within an organization is called a(n):
查看答案
D. grapevine
4单选题4 / 39
by which process may an unsuccessful supplier seek remedy for unjust awards?
查看答案
C. bid protest
5单选题5 / 39
risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):
查看答案
B. should be handled via contingency allowances
7单选题7 / 39
the major difference between project and line management is that the project manager may not have any control over which basic
management function?
查看答案
B. staffing
8单选题8 / 39
which of the following planning considerations is often overlooked?
查看答案
A. planning for project termination.
9单选题9 / 39
a recurring communication pattern within the project organization or company is called a:
查看答案
C. network
10单选题10 / 39
during a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12%
of the work scheduled to this point of time. you can therefore conclude that:
查看答案
E. none of the above.
11单选题11 / 39
once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. this will
provide information on the (    ) and identification of the (    ) .
查看答案
A. slack for each activity, critical path.
12单选题12 / 39
risk can be divided into two basic types; business risk and pure (or insurable risk). of the following, which one(s) fall(s) under business risk?
查看答案
C. profit loss
13单选题13 / 39
the purpose of project risk management is to:
查看答案
E. all of the above.
14单选题14 / 39
which of the following factors has historically been the greatest contributor to project failure?
查看答案
D. lack of management support.
15单选题15 / 39
which type of process involves the agency holding discussions with each of the offerors, after receipt of their proposals, in the process of
arriving at an agreement prior to the award of a contract?
查看答案
B. competitive proposals
16单选题16 / 39
a non-critical path activity is completed in half the time. then,
查看答案
B. the slack in the path containing this activity will increase.
17单选题17 / 39
an element in the wbs was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50k. the task was
completed in 1000 hours but a burdened cost of $60k. the most likely reason for the increase would be:
查看答案
E. any of the above
18单选题18 / 39
in the past, most project managers have come from (    ) fields without proper (    ) training or education in skills
查看答案
B. technical; management
19单选题19 / 39
the risk of not meeting project quality objectives:
查看答案
E. all of the above.
20单选题20 / 39
the main player in project communication is the
查看答案
B. project manager
21单选题21 / 39
the type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that
project. for a firm fixed price contract, payment for risk (    ) .
查看答案
C. is an undisclosed contingency in the contractor's bid.
22单选题22 / 39
which is not an element of procurement management?
查看答案
C. marketing
23单选题23 / 39
which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
查看答案
D. 0.25
24单选题24 / 39
bar charts are most appropriate for:
查看答案
A. comparing actual to planned performance to each activity.
25单选题25 / 39
formal authority is often referred to as legitimate power. which two other forms of power are also considered to be legitimate power?
查看答案
A. reward and penalty
26单选题26 / 39
power games, withholding information, and hidden agendas are examples of-.
查看答案
B. communication barriers
27单选题27 / 39
scope management is:
查看答案
E. all of the above.
28单选题28 / 39
the most common method for pricing out non-burdened labor hours for a three year project would be to:
查看答案
C. price out the work using a functional group average labor rate.
29单选题29 / 39
the principles of risk management should be followed only for:
查看答案
E. all of the above.
30单选题30 / 39
utility theory:
查看答案
A. considers the risk propensity of the decision makers.
31单选题31 / 39
which is not part of the purchasing cycle?
查看答案
C. inspection
32单选题32 / 39
a network has been developed with resources from six different departments. one of the six departments has just informed you that they can
increase the number of employees from 5 to 8. this will result in:
查看答案
E. a through d are possible based upon where the resources are deployed.
33单选题33 / 39
conflict management requires problem-solving. which of the following is often referred to as a problem-solving technique and used
extensively in conflict resolution?
查看答案
A. confrontation
34单选题34 / 39
cost reimbursable contracts are equivalent to:
查看答案
A. cost plus contracts
35单选题35 / 39
in project-driven companies, costs are usually billed againest the project based upon:
查看答案
A. the burdened labor rate of the actual employees who performed the work.
36单选题36 / 39
project risk management is based on which of the following premises:
查看答案
E. all of the above.
37单选题37 / 39
the project manager that allows and supports group discussions and decision making is called a(n) (    ) manager.
查看答案
C. consensus
38单选题38 / 39
what is the purpose of the project plan?
查看答案
C. to document the budgetary estimates.
39单选题39 / 39
management has decided to "crash" a project in order to avoid penalty payments for late deliveries. to crash the project, either overtime or
additional resources should be assigned to:
查看答案
C. those activities on the critical path begining with the longest time duration activities.
← 上一卷下一卷 →