there are two major types of reserves used on projects. the (    ) is for (usually major) scope changes that were not considered as part of
the original plan, whereas the (    ) is to compensate for minor changes in estimating, escalation factors.
查看答案
C. contingency fund, management reserve.
2单选题2 / 40
to determine what causes the majority of quality problems in a process, a very useful tool is the:
查看答案
D. pareto chart.
3单选题3 / 40
which of the following is not part of contract administration
查看答案
A. contract award
4单选题4 / 40
a(n) (    ) system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight,
storage and loss.
查看答案
B. materials management.
5单选题5 / 40
expectancy theory as applied to project management implies that:
查看答案
C. team members will work hardest for those project goals that also bring satisfaction to personal goals
6单选题6 / 40
non-verbal communication includes:
查看答案
E. all of the above
7单选题7 / 40
the formal invitation to submit a price for specified goods/services is usually referred to as:
查看答案
B. request for quotation
8单选题8 / 40
the project scope/charter baseline includes:
查看答案
E. all of the above.
9单选题9 / 40
which of the following is not an input to quality planning?
查看答案
C. work results.
10单选题10 / 40
which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous
element has been completed?
查看答案
C. pdm
11单选题11 / 40
which of the following utility functions reflects risk-aversion:
查看答案
C. decreasing
12单选题12 / 40
a deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as:
查看答案
C. non-conformance
13单选题13 / 40
a line manager possesses information which the project team needs, but withholds the information. the results in a(n):
查看答案
B. facade
14单选题14 / 40
a project can best be defined as:
查看答案
D. any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain
constraints.
15单选题15 / 40
guidelines for estimating time durations include:
查看答案
E. all or part of each of the above.
16单选题16 / 40
herzberg identified factors which, if present, will lead to increased motivation. a typical factor would be:
查看答案
C. regular promotions
17单选题17 / 40
statistical cost estimating techniques (based upon history), are called (    ) estimates and are a (    ) approach.
查看答案
D. parametric, top down.
18单选题18 / 40
which quality management tool would be used to determine potential causes of a production problem?
查看答案
B. ishikawa diagram.
19单选题19 / 40
affinity diagrams are used to:
查看答案
D. categorize large amounts of data.
20单选题20 / 40
one of your project team members has made a technological breakthrough on an r & d project. the result will be new business for the
company, as well as a company patent. the team member received a company bonus. the motivational strategy used here is:
查看答案
B. linking pay and performance
21单选题21 / 40
smoothing out resource requirements from period to period is called resource (    ).
查看答案
C. leveling.
22单选题22 / 40
the most precise or accurate estimate for determining project costs is the (    ) estimate.
查看答案
A. definitive.
23单选题23 / 40
when subordinates know pertinent information that is not known by the project manager, the result is:
查看答案
A. blindspot
24单选题24 / 40
which of the following scheduling methods uses more of the risk management concepts:
查看答案
D. pert
25单选题25 / 40
which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:
查看答案
B. substantial completion
26单选题26 / 40
a (    ) estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
查看答案
C. budget
27单选题27 / 40
assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource (    ).
查看答案
A. allocation.
28单选题28 / 40
for communication to occur, there must be:
查看答案
D. all of the above
29单选题29 / 40
the ability to get an individual or group to perform a given task is best described as:
查看答案
B. power
30单选题30 / 40
the comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:
查看答案
E. contractor's performance evaluation
31单选题31 / 40
the financial closeout of a project dictates that:
查看答案
D. no further charges can be made against the project.
32单选题32 / 40
two sources of variation in the length of hex bolts exist. production variation and measurement error. the qc manager knows that the
standard deviation from these sources is 0.24" and 0.43" , respectively. what is the total standard deviation.
查看答案
D. .49 inch.
33单选题33 / 40
which of the following activities can be considered as part of risk mitigation
查看答案
B. purchasing insurance
34单选题34 / 40
in general, attempts to smooth out period to period resources will (    ) the scheduled time and (    ) project costs.
查看答案
B. increase, increase
35单选题35 / 40
risk management methodology should be adhered to in:
查看答案
E. all of the above.
36单选题36 / 40
the most common form of written project communication is
查看答案
D. letters and memos
37单选题37 / 40
the most difficult decision for the executive sponsors to make at the end-of-phase review meeting is:
查看答案
D. canceling the project.
38单选题38 / 40
the most expensive phase of life cycle costing is:
查看答案
D. operations and support.
39单选题39 / 40
the rule of seven used by quality control engineers states that if a run of seven or more samples lays on one side of the process mean, then
the process is out of control. what is the probability that this condition is the result of random variations.
查看答案
D. 0.0156
40单选题40 / 40
the term that best describes the 'right' to manipulate or change others is called?
查看答案
A. authority