职业资格类项目管理师PMP美国项目管理PMP

PMP认证考试练习题(3.4)

40 题含答案PMP
共 40 题返回本类
1单选题1 / 40
management decision-making includes:
查看答案
E. all of the above.
2单选题2 / 40
the basic terminology for networks includes:
查看答案
C. slack, activities, events, and time estimates.
3单选题3 / 40
the project manager must receive reports and briefings from engineers, contracting officers, procurement personnel and marketing people.
the project manager's communication dilemma is one of:
查看答案
E. all of the above.
4单选题4 / 40
the technique most commonly used to determine the profitability of a project includes (    ) methods.
查看答案
E. all of the above.
5单选题5 / 40
which of the following are part of the purchasing cycle:
查看答案
E. a and b only
6单选题6 / 40
which of the following is closest to juran's definition of quality:
查看答案
B. fitness for use.
7单选题7 / 40
a project element which lies between two events is called:
查看答案
A. an activity.
8单选题8 / 40
employee unions would most likely satisfy which level in maslow's hierarchy of needs?
查看答案
A. belonging
9单选题9 / 40
management calls a meeting to explain to all employees the new benefits package for the rank and file. this is an example of:
查看答案
C. one-way communication
10单选题10 / 40
project management/project planning is most closely aligned with:
查看答案
E. b and c
11单选题11 / 40
the profitability and technical data studies are provided in report format to owners and funders for acceptance. this type of report, used to solicit funding, is referred to as a(n) (    ).
查看答案
D. prospectus.
12单选题12 / 40
which of the following constitute juran's "quality trilogy":
查看答案
B. planning, improvement, control.
13单选题13 / 40
which of the following is most closely associated with business risk:
查看答案
A. profit and loss
14单选题14 / 40
which of the following types of contracts is equivalent to a cost plus contract:
查看答案
B. cost reimbursable
15单选题15 / 40
a project manager recently rewarded an individual with a promotion that carried with it a very small salary increase but substantially more
responsibility. the project manager appears to be appealing to the employee's (    ) need.
查看答案
C. esteem
16单选题16 / 40
most project (and non-project) managers prefer (    ) communications.
查看答案
A. oral
17单选题17 / 40
on a precedence diagram, the arrow between two boxes is called:
查看答案
B. a constraint.
18单选题18 / 40
quality control charts show a characteristic of the product or service against:
查看答案
C. control limits based on three standard deviations in each direction.
19单选题19 / 40
the identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are
indentified in the (    ) phase of the project but first documented in the project (    ).
查看答案
A. conceptual, charter/baseline.
20单选题20 / 40
the work breakdown structure, the work packages, and the company's accounting system are tied together through the:
查看答案
A. code of accounts.
21单选题21 / 40
which of the following is an element of procurement management:
查看答案
E. a, b and d only
22单选题22 / 40
which of the following is most closely associated with pure risk:
查看答案
C. insurance
23单选题23 / 40
assignable cause or special variation is:
查看答案
E. a, c, and d
24单选题24 / 40
in the arrow diagramming method (adm), (    ) do not consume time or resources.
查看答案
A. events.
25单选题25 / 40
management reserve is generally intended to be used to:
查看答案
D. cover unforeseen problems in the project
26单选题26 / 40
project management has been proven to be successful because employees get to see the entire effort, from beginning to end, rather than just
small pieces. this could be considered an example of:
查看答案
D. job enrichment
27单选题27 / 40
project managers that are available to answer questions, provide guidance when need, and generally do not interfere with day-to-day activities
have a(n) (    ) managerial style.
查看答案
D. facilitative
28单选题28 / 40
the scope baseline once established and approved, is used:
查看答案
D. all of the above.
29单选题29 / 40
the three most common types of project cost estimates are:
查看答案
D. order of magnitude, budget and definitive.
30单选题30 / 40
to calculate the expected value of an outcome:
查看答案
C. multiply the value of each outcome by its probability, then add the results
31单选题31 / 40
activities with zero time duration are referred to as:
查看答案
D. dummies
32单选题32 / 40
for a given characteristic in a construction process, the standard deviation associated with production variation is 0.8", and the standard deviation associated with measurement variation is 0.6". the total standard deviation for this
characteristic is:
查看答案
C. 1.0"
33单选题33 / 40
project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
查看答案
A. overhead rates, labor rates and material costs.
34单选题34 / 40
selective perception is (    ) of new conflicting information that may result, in a breakdown in communication.
查看答案
B. blocking out
35单选题35 / 40
the work breakdown structure (wbs) is an excellent tool for objective control and evaluation. which of the following is generally not
validated through the wbs?
查看答案
D. quality of work.
36单选题36 / 40
when working in an environment that uses learning curves, the most effective plan for creating the perception that pay is related to
performance is to provide the team members with an individual salary plus bonus based upon
查看答案
A. individual productivity
37单选题37 / 40
which of the following is not part of the acquisition process:
查看答案
D. notice to proceed
38单选题38 / 40
an individual who is working on the satisfaction of physiological needs has essentially satisfied which needs?
查看答案
E. none of the above
39单选题39 / 40
in the pdm, common constraints include:
查看答案
E. a, b, and c
40单选题40 / 40
scope reporting is the timely determination, (    ), and (    ) of project progress, status data, and transforming this into structured
documentation (reports) necessary to judge project performance (reporting on work packages).
查看答案
A. recording, accumulation.
← 上一卷下一卷 →