“Force Majeure” means an exceptional event or circumstance like ( )
查看答案
A. which is beyond a Party’s control, B. war, invasion, act of foreign enemies, C. Which, having arisen, such Party could not reasonably have avoided or overcome, D. natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity.
A. the Contractor subcontracts the whole of the Works without the required agreement, C. the execution of substantially all the Works in progress is prevented for a continuous period of 84 days by reason of Force Majeure, D. the Employer substantially fails to perform his obligations under the Contract,
A. war hostilities B. pressure waves caused byaircraft, C. rebellion, terrorism, revolution or usurped power or civil war, within the Country, D. riot within the Country by the Contractor’s Personne
The Employer may claim the full amount of thePerformance Security when ()
查看答案
A. the Contractor failed to extend the validity of the Performance Security; B. the Contractor failed to pay the Employer an amount due, as either agreed by theContractor or determined under Sub-clause 2.5 [Employer’s Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement or determination, D. circumstances which entitle the Employer to termination,
Within 42 days after the Contractor became aware of the event giving rise to the claim, the Contractor shall send to the Employer a fully detailed claim.
If the event or circumstance is natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity, the Contractor shall be entitled to payment of any such Cost.
If the Employer intends to make any material change to his financial arrangements, the Employer shall give notice to the Contractor with detailed particulars.
The Employer shall return the Performance Security to the Contractor within 21 days after the Contractor has become entitled to receive the Performance Certificate.