1单选题1 / 30
Prior to the commencement ofthe Tests on Completion, the Contractor shall submit  (  ) to the Engineere
查看答案
C. the operation and maintenance manuals
2单选题2 / 30
The Employer shall give theContractor not less than (   ) hours’ notice of theEmployer’s intention to attend the tests. 
查看答案
A. 12
3单选题3 / 30
If the number is not so statedand the Parties do not agree otherwise, the DAB shall comprise ( ) persons. 
查看答案
C. 3
4单选题4 / 30
Performance of the Contractor’s obligations shall not be considered to have been completed until the Employer has issued the (   ) to the Contractor.
查看答案
D. Performance Certificate
5单选题5 / 30
The Employer shall issue the Performance Certificate within ( ) days after the latest of the expiry dates of the Defects Notification Periods.
查看答案
B. 28
6单选题6 / 30
The () shall appoint the Contractor’s Representative and shall give him all authority necessary to act on the Contractor’s behalf under the Contract.
查看答案
A. Contractor 
7多选题7 / 30
“Force Majeure” means an exceptional event or circumstance like (  ) 
查看答案
A. which is beyond a Party’s control, B. war, invasion, act of foreign enemies, C. Which, having arisen, such Party could not reasonably have avoided or overcome, D. natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity.
8多选题8 / 30
The Contract can be terminated when(  )
查看答案
A. the Contractor subcontracts the whole of the Works without the required agreement, C. the execution of substantially all the Works in progress is prevented for a continuous period of 84 days by reason of Force Majeure, D. the Employer substantially fails to perform his obligations under the Contract,
9多选题9 / 30
Employer’s Risks referred to()
查看答案
A. war hostilities   B. pressure waves caused byaircraft,  C. rebellion, terrorism, revolution or usurped power or civil war, within the Country, D. riot within the Country by the Contractor’s Personne  
10多选题10 / 30
The Employer may claim the full amount of thePerformance Security when ()
查看答案
A. the Contractor failed to extend the validity of the Performance Security;  B. the Contractor failed to pay the Employer an amount due, as either agreed by theContractor or determined under Sub-clause 2.5 [Employer’s Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement or determination,  D. circumstances which entitle the Employer to termination, 
11多选题11 / 30
The Contractor shall, as specified in the Contract or as instructed by the Employer, allow appropriateopportunities for carrying out work to: 
查看答案
A. the Employer’s personnel  B. any other contractors employed by the Employer  C. the personnel of any legally constituted public authorities
12判断题12 / 30
Within 42 days after the Contractor became aware of the event giving rise to the claim, the Contractor shall send to the Employer a fully detailed claim. 
查看答案
A. 正确
13判断题13 / 30
For a DAB of three persons, the DAB shall be deemed to have received such reference on the date when it is received by the chairman of the DAB.
查看答案
A. 正确
14判断题14 / 30
If the event or circumstance is natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity, the Contractor shall be entitled to payment of any such Cost. 
查看答案
B. 错误
15判断题15 / 30
The Employer shall take full responsibility for the care of the Works and Goods from the Commencement Date until the Taking-OverCertificate is issued. 
查看答案
B. 错误
16判断题16 / 30
If the Employer intends to make any material change to his financial arrangements, the Employer shall give notice to the Contractor with detailed particulars. 
查看答案
A. 正确
17判断题17 / 30
The Contractor shall deliver the Performance Security to the Employer within 21 days after bothParties have signed the Contract Agreement.  
查看答案
B. 错误
18判断题18 / 30
The Engineer shall be responsible for the adequacy, stability and safety of all Site operations, of allmethods of construction and of all the Works. 
查看答案
B. 错误
19判断题19 / 30
The Employer shall return the Performance Security to the Contractor within 21 days after the Contractor has become entitled to receive the Performance Certificate. 
查看答案
A. 正确
20判断题20 / 30
The Employer may appoint an Employer’s Representative to act on his behalf under the Contract.  
查看答案
A. 正确